Skip to main content
Airport City Bank — Epoxy Trading Floor
Banking & Financial · 2024 · 2,400 m²

Airport City Bank — Epoxy Trading Floor

Self-levelling epoxy with ESD dissipation. Installed across 72 hours to protect trading operations.

Client
Major Ghanaian Bank
Location
Airport City, Accra
Sector
Banking & Financial
Area
2,400 m²
Completed
2024
Service

The Challenge

A leading Ghanaian bank's Airport City trading floor required complete re-flooring after twelve years of heavy institutional use. The existing tile had begun to lift, present trip hazards, and interfere with ESD-sensitive trading equipment. Replacement had to happen without disrupting Monday morning trading — giving the installation team a total window of 72 hours from Friday 18:00 to Monday 05:00.

Our Solution

Our War Room specified 3mm self-levelling epoxy with integrated ESD dissipative layer and conductive copper grid beneath. The grid was bonded to the building's electrical earth at three points across the 2,400 m² floor. The epoxy itself was formulated for accelerated cure — trafficable in 12 hours, fully operational in 48. A phased installation across four zones allowed our teams to work in parallel while maintaining continuous substrate preparation ahead of the resin teams.

Project Timeline

How the Installation Actually Unfolded

01

Friday 18:00

Existing tile removal commences. Bank equipment pre-cabled around work zones.

02

Saturday 02:00

Substrate mechanical grinding and moisture testing across all four zones.

03

Saturday 10:00

Copper grid installation and bonding to building earth. Grid certified by third-party surveyor.

04

Saturday 18:00

Primer coat applied. 12-hour cure window begins.

05

Sunday 10:00

Self-levelling epoxy poured across Zones A and B. Zones C and D prepared in parallel.

06

Sunday 22:00

Final zones poured. All resin in place by midnight.

07

Monday 04:30

Resistance testing at 24 measurement points. All within ESD compliance. Handover to facilities team.

The Outcome

Monday 06:00 trading opened on schedule. Zero disruption to institutional operations. The floor has now been in continuous service for two years with no defects, no lippage, and no resistance drift from its commissioning measurements. Bank facilities team has since specified Floors GH for three additional branch retrofits across Accra and Tema.

We chose Floors GH after three competitors told us our timeline was impossible. They did not just meet it — they finished four hours ahead of schedule. The floor they installed is still performing exactly as commissioned two years later. For a bank, that kind of reliability is not a luxury. It is a business necessity.

Director of Facilities, Major Ghanaian Bank
Floors GH team at work
Every case study represents work our own specialists installed — no subcontractors, no shortcuts.

Have a Similar Project? Let's Talk.

Every project begins with a free on-site survey. A specialist will respond the same business day.

Request Free Site Survey All Case Studies
Request Quote